The Birchwood Construction Update as of December 2015


The Birchwood in Acacia Estates, Taguig City

Turnover Dates:

Alder – Dec 2016

Evergreen – March 2017

Oleander – September 2017

Calathea – January 2018

Maple – January 2018

Updates:

Over-all construction status of the site : 32.29%

Alder : 45%. On-going Masonry Works at Exterior and Atrium; On-going MEPF Works.

Evergreen : 40.00%. On-going Masonry works at Elevator Deck (Parapet Wall).

Clubhouse - 15%. On-going structural works at Level 2.

OLEANDER - 25%. On-going structural works at Parapet Wall - Suspended Slab and Columns; On-going installation of formworks at Parapet Wall. ; MAPLE - 8%. On-going Structural Works at UGF - Columns and Slabs. ; CALATHEA - 8%. On-going structural works at LGF (Columns and Suspended Slab).