Turnover Dates:
Alder – Dec 2016
Evergreen – March 2017
Oleander – September 2017
Calathea – January 2018
Maple – January 2018
Updates:
Over-all construction status of the site : 32.29%
Alder : 45%. On-going Masonry Works at Exterior and Atrium; On-going MEPF Works.
Evergreen : 40.00%. On-going Masonry works at Elevator Deck (Parapet Wall).
Clubhouse - 15%. On-going structural works at Level 2.
OLEANDER - 25%. On-going structural works at Parapet Wall - Suspended Slab and Columns; On-going installation of formworks at Parapet Wall. ; MAPLE - 8%. On-going Structural Works at UGF - Columns and Slabs. ; CALATHEA - 8%. On-going structural works at LGF (Columns and Suspended Slab).