Verawood Residences Construction Update as of December 2015


Verawood Residences in Acacia Estates, Taguig City

Turnover Dates:

Wisteria – July 2015

Marsala – September 2015

Peridot – November 2015

Canary – February 2016

Aqua – May 2016

Flamingo – September 2016

Lime – December 2016

Updates:

-Wisteria building: 100%. All floors completed. Accepted by QMD. Dressed up all units. Marsala building: 99.55%. All floors completed. Accepted by QMD. On-going dress up of units.

-Peridot building: 95.97%. All floors completed. On-going QMD acceptance. On-going dress up of units. Canary building: 75.62%. All floors completed. On-going bare units and finishing works.

-Aqua building; 56.80%. All floors completed. On-going masonry works. Lime building: 47.34% All floors completed. Structural works completed. Exterior canopy works. CLUBHOUSE: 96.83%. Accepted by QMD. AMENITIES: 99.21%. Accepted by QMD.

-Flamingo building: 50.20%. All floors completed. Structural works completed. On-going elevator shaft enclosure.